Before the widening
Behind the visitors in Sandra Ortiz Yang’s photo, the concrete meets a band of exposed rock. This is the old launch seen from ground level.
Sandra Ortiz Yang on Tripadvisor
In 1992, a boat couldn’t get out of the marina. In 2024, fishermen parked their boats in front of City Hall because they could barely get into the sea.
The boats were still on their trailers. That morning, fishermen blocked PR-115 between the plaza and Rincón’s town hall. They wanted somewhere to park a trailer and a clear path down the ramp when it was time to put a boat in the water.
Eight months later, a visitor named Dan left directions for snorkeling at Black Eagle. “Swim from boat ramp, North/right around rocks,” he wrote on Google. You can picture the problem from either end of the trailer. The easiest place to walk into the sea was also where a fisherman had to back a boat into it.
There used to be another way out. On November 4, 1992, the Border Patrol needed an emergency dredging permit to free a boat trapped inside the marina. Sand had blocked the channel. By 2004 the basin had closed. The fishermen’s route moved northeast, to a strip of concrete on the open cove.
The 1992 permit authorized removal of 50 cubic yards. The Corps dates the basin closure to 2004 and places construction of the outside launch after closure. The Tres Palmas management plan records landings near the marina in 2005–07. The exact opening day of the outside slab is unknown.
Primera Hora reported Marimar Bonet’s Facebook Live account of the protest. The swimmer’s directions come from a Google review posted January 7, 2025, reproduced by Wanderlog.
Protest reporting · Dan H’s Google review · Army Corps permit history · Tres Palmas plan
In the first photograph there is a curve of beach and a stand of trees. By 1999 there is a dark rectangle where boats could tie up. Follow it to the water. The basin is still easy to find. Its way out is harder to see.

The basin19631999The 1981 permit authorized a breakwater, ten finger piers and a channel. USGS dates construction to 1983. A 1985 permit included a 41-by-12-foot concrete ramp at the marina. A 1995 permit allowed periodic dredging. The Corps declined another application in 2002.
All four aerials share one north-up extent centered at 18.344153° N, 67.260165° W. The 1999 image has glare. The 2017 mosaic was flown September 27–October 8. Tide, surf and image resolution differ. The closure date and the later description of a beach at the mouth come from the Corps. The frames do not independently establish water depth, the date the sand arrived or when the mouth became walkable.
Army Corps history and drawings · USGS construction history · USDA aerials · NOAA mosaic · 2017 acquisition record
By the time engineers looked at reopening the basin, the old entrance was a beach. Underwater, mountainous star coral had grown on the south breakwater. A structure built for boats had become habitat for a protected species.
The bottom changed within a short swim. There was fine, dark sediment inside the basin, loose sand in the channel, and coral on the rocks outside. Reopening the old route meant excavating across that boundary and keeping it clear the next time sand moved in.
Winter Storm Riley offered one answer in March 2018. At the nearby Balneario, crews surveyed the beach and seabed. The berm lost sand. Along one survey line, the bottom gained sediment under two to four metres of water. Someone standing on shore could see the loss and miss the gain entirely.

The often-cited figure is 1.1 metres a year. USGS measured it along a stretch south of the Balneario over 70 years, starting in 1936. The beach had already retreated sharply by 1971 and recovered substantially by 1974. The marina was built in 1983. Its effect is harder to isolate than the number suggests.
The Corps described apparent northward sediment movement at the entrance. In 1995 it allowed dredged sand to be placed south of the mouth. The 2019 application proposed moving channel sand to the adjoining beach and finer basin material upland. Proposed placement volumes are not receipts for sand actually moved.
The Riley survey was at the public beach, away from the launch. Its profiles cannot trace individual grains to the ramp. The protected coral finding comes from a July 2016 survey summarized in the Corps notice.
The USGS rate for Reach B extends to 500 metres south of Quebrada los Ramos. The report published in 2007 revisited an earlier inference about the marina. Its 1936–2006 reach averages are shown below.
Average shoreline retreat in metres per year, 1936–2006. Bars show magnitudes. The ± values are USGS’s reported uncertainties.
Corps habitat assessment · Riley surveys · Early USGS assessment · Longer USGS record
Rincón first proposed digging the marina back out. The 2019 plan called for extending both breakwaters and removing more than 5,600 cubic yards of sand and sediment from the entrance and basin. Public and agency comments sent the town back to its drawings.
The revised design started at the trailer wheels. The outside slab was about four metres wide. The municipality proposed eight metres at its landward end and ten at the water, with rock along one edge and a flexible concrete mat under the water. A wider landing would give a driver more room to retrieve a boat in waves.
In June 2026 the town inaugurated the outside ramp, paved the lot, marked trailer spaces and put up signs for swimmers. The reported $1.1 million covered the waterfront project. The basin beside it stayed closed.
The 2019 estimates were 2,354 cubic yards at the entrance and 3,270 in the basin, before excavation allowances. The 2020 application gives the old slab as roughly 26 by 4 metres. The proposed widths are design dimensions. An as-built survey would establish the finished dimensions.
FEMA listed $13,699.81 for design. The 2023 recovery plan connected the widening to local fisheries. Bids were due June 11, 2025, under PN 107836 / PW 3854. The opening report does not itemize the $1.1 million or settle whether it includes the earlier design allocation.
2019 application · 2020 redesign · FEMA design allocation · Recovery plan · Bid listing · Opening coverage
One person photographed a day at the beach. Another left directions. Read together with the protest and opening photographs, those small details show what the concrete looked like, who needed it and how the rebuilt ramp met the water.

Behind the visitors in Sandra Ortiz Yang’s photo, the concrete meets a band of exposed rock. This is the old launch seen from ground level.
Sandra Ortiz Yang on Tripadvisor
The trailers between the plaza and City Hall show how far the dispute over access had traveled.
Protest and Facebook Live account in Primera Hora“Swim from boat ramp, North/right around rocks”
Dan H used the concrete as the starting point for a snorkeling route. The directions put a swimmer in the very lane the fishermen wanted clear.
Google review reproduced by Wanderlog
In the opening coverage a boat sits on its trailer at the water. A second frame looks straight back up the new slab. That frame anchors the field station below.
Metro Puerto Rico opening photographsA beach tag can place a picture in Rincón without putting the ramp in frame. A 2009 video has an upload date. A travel photographer’s image shows the shoreline but misses the slab. An undated gallery shows the rocks. An August 2025 review describes seaweed over sand. All four help locate the place, but none dates a change at the ramp edge.
The four-metre width comes from the 2020 application. The 2017 visit photo supplies the visible edge. June 3 is the date of the opening report. The Google entry is written testimony.
2009 Black Eagle video · @DRIMedia shoreline photograph · Undated beach gallery · August seaweed report
Open the place pin · Search Google Images · Search public Instagram posts
Here is the edge to watch after a northwesterly swell. At opening, you could follow the straight seam between concrete and rock almost to the foam. How much of it can you see now?

The first verified shore-based repeat will establish the matching land view.
The press photograph was taken from offshore. It identifies the edge to find from land. The repeat position uses the landward corner of that edge as its landmark. Subsequent shore photographs can be compared with one another. The red line marks a feature and provides no scale for sand depth.
The search checks publicly discoverable posts. Each verified, voluntary tagged shot gets a dated log entry that links back to its public source. Private posts and stories that have disappeared cannot be checked. We distinguish exposed concrete, sand cover and views obscured by foam. The share control prepares a dated copy on your device. Nothing is sent to this site.